The project extended a sanitary sewer line from U.S. Highway 78 to the north terminal area. It provides the necessary connection to the Athens-Clarke County sanitary sewer system to serve current and proposed future airport development.
Budget
- Original SPLOST Budget: $882,340
- Budget Amendments: $231,873
- Adjusted SPLOST Budget: $1,114,213
- Amount Expended: $1,114,213