The project demolished the existing operations center facility and constructed a new facility comprised of multipurpose community / educational space, an administrative office, meeting spaces for park staff, restrooms, kitchen spaces, and approximately 40 additional parking spaces. It also consisted of preparing a general plan for Memorial Park identifying all future areas of development.
Budget
- Original SPLOST Budget: $1,622,000
- Budget Amendments: $134,232
- Adjusted SPLOST Budget: $1,756,232
- Amount Expended: $1,756,216
|
|