The project upgraded and improved major transit stops along the Athens Transit Bus System routes. The improvements for these transit stops were evaluated for their specific needs. Improvements include:
- Bicycle racks
- Bus pull-off to allow traffic to have a clear lane while the bus is loading and unloading
- Installation of proper signage, a paved pad, benches, and a covered shelter
- Landscaping
- Route information
Budget
- Original SPLOST Budget: $1,167,792
- Budget Amendments: -$167,721
- Adjusted SPLOST Budget: $1,000,071
- Amount Expended: $999,738
|
 |