Pavement Maintenance Program

The roadway list for the 2020 Pavement Maintenance Program was approved by Mayor and Commission on March 3, 2020.

The total budget for this year’s work is $6,600,000 and is being funded by General Capital Fund, SPLOST 2011, TSPLOST 2018, GDOT Local Maintenance and Improvement Grant (LMIG) and Public Utilities General Capital Fund.

A total of 44 roadway segments are approved for prevention treatment, totaling approximately 42.08 lane-miles of surface.

Paving activities kicked off on July 13, 2020. Substantial Completion for this year’s program is set for October 30, 2020. This work is subject to disruption due to weather or other unforeseen circumstances. 

During the week of September 21, crews will be working the following streets:

  • Takeda Way
  • Oak Drive
  • Oak Park Court
  • Longbranch Court
  • Blackmore Court
  • Faulkner Drive
  • Arbor View Drive
  • Booker Street
  • Branch Street
  • Conrad Drive
  • Dublin Street
  • E. Broad Street
  • First Street


Road / Lane closings may occur in short duration.

Please visit the Road & Lane Closure page for a complete listing of weekly closings.