Sub-Project 6: Carr's Creek / Barnett Shoals Road

Project Details

Project Concept was approved by the M&C on July 5, 2016.  The Preliminary Plans were approved by M&C on January 3, 2017. 

Project Updates

Land for Sub-Project #6 has been acquired.  Because ACCGov now owns all of the adjacent land. Revised Preliminary Plans were approved by M&C at the September 7, 2021 voting meeting.  Final design is complete and has been combined with Sub-Project #4.2 - #4.3.

Key Project Statistics

  • Designer: TBD
  • Contractor: TBD
  • Program Manager: Jacobs Engineering
  • Original SPLOST Budget: $630,000
  • Total Cost: TBD
  • Completion Date: TBD