Project Details:
Project Concept was approved by the M&C on August 4, 2015. The Project User Group has initiated review/planning meetings. Preliminary Plans were approved by M&C on September 6, 2016.
Segment 4.1 was completed November 7, 2018.
Project Updates:
Project schedule for Sub-Projects #4.2 and #4.3 being delayed due to land acquisition waiting on T&PW and PUD to complete other work on adjacent property before continuing land acquisition task.
Key Project Statistics
- Designer: W R Toole
- Contractor: To be determined
- Program Manger: Jacobs Engineering
- Sponsor: Leisure Services
- Original SPLOST Budget: $2,460,000
- Amended Budget: To be determined
- Total Cost: To be determined
- Completion Date: To be determined
*as of 10/15/2019