Sub-Project 2: Streets & Drainage Solar Panels

Project Summary

Construction of a solar energy array at the Streets & Drainage Facility. Oversight Committee approved the Project Concept on April 24, 2017. Project was completed September 1, 2017.

Key Project Statistics

  • Project Contractor: Solar Sun World LLC
  • Program Manager: Jacobs Engineering
  • Original SPLOST Budget: $46,519
  • Grants or other funding: $50,000
  • Total Cost: $96,419
  • Completion Date: September 2017