Project Details
On December 7, 2016 a Project Concept for Sub-Project #9 was approved by the M&C. The Sub-Project includes the complete resurfacing of the parquet wood gym floors at East Athens Community Center and at Lay Park Community Center. This sub-project was completed December 2017.
Key Project Statistics
- Contractor: FloorCare Specialists, Inc.
- Program Manager: Jacobs Engineering
- Sponsor: Leisure Services
- Original SPLOST Budget: $31,360
- Total Cost: $31,360
- Completion Date: December 2017