Sub-Project 11: Playground Repair

Project Details

On December 7, 2016 a Project Concept for Sub-Project #11 was approved by the M&C. The Sub-Project includes the rehabilitation of the playground equipment at Satterfield Park. This sub-project was completed December 2017.

Key Project Statistics

  • Contractor: Play Power
  • Program Manager: Jacobs Engineering
  • Sponsor: Leisure Services
  • Original SPLOST Budget: $58,978
  • Amended Budget: $58,963
  • Total Cost: $58,963
  • Completion Date: December 2017


Project 16, sub-project 11 - playground at satterfield park