Project Details
This sub-project is to provide rehabilitation of the beach area including relocation of the beach showers, re-grading the beach area, installation of a new drainage system and rehabilitation of beach shower drains would alleviate the erosion issues. New sand would be installed on the beach upon completion of the drainage improvements. M&C approved the Project Concept June 4, 2019.
Project Update
The rainy weather conditions delayed the start of construction on this project, and the pandemic put some of the work on hold. New showers and beach sand will be installed prior to the park reopening but full restoration of the beach is planned to begin after the beach closes for the season with completion anticipated in Fall 2020.
Project Statistics
- Designer: W R Toole
- Contractor: Structural Resources, Inc.
- Program Manager: Jacobs Engineering
- Sponsor: Leisure Services
- Original SPLOST Budget: $154,470
- Total Cost: TBD
- Projected Completion Date: Fall 2020
*as of 04/30/2020