Project 3: Bus Stop & Transfer Facilities Improvement Project

Project Statement

The Bus Stop & Transfer Facilities Improvement Project includes transit related improvements for the land acquisition, design, and construction of decentralized transit transfer facilities outside of the downtown terminal.  Also, for the capital improvements of signage (static and/or electronic predictive arrival), concreate pads, seating, covered shelters over the paved pad, landscaping, lighting, route information, bicycle racks, trash cans, bus pull-offs, restroom facilities, bus/customer parking and other related bus stop improvements, as deemed appropriate by location. This funding may also be used to match funding for state and/or federal grants for additional transfer facilities or bus stop improvements. 

Project Update

ACCGov Transit has been awarded an FTA/GDOT 5339 discretionary grant for funding to identify and procure property, design, and complete a NEPA for a Remote Transfer Facility has been approved by GDOT and FTA. The approved grant is $400,000, with a required $100,000 local match, bringing the project total to $500,000.   This discretionary grant application was approved by the Mayor & Commission and submitted in November 2019. It identified matching funds from the 2018 TSPLOST Project # 3, as a local match.  The original application was for $1,000,000, with a $250,000 local match. However, this grant only provides for $400,000 of Federal funding, and requires a $100,000 local match.  

The Proposed Project Concept for the Transfer Facility for the Mall Redevelopment area was presented to the Oversight Committee on April 15, 2024, and the Mayor & Commission approved the project concept on May 7, 2024.  Schematic Design for the Mall Transfer Facility is ongoing.  Anticipate presentation to M&C in early 2025.

Site Layouts and Traffic warrant analysis for a Transfer Facility at SE Clarke Park with an associated Traffic Signal is underway.  Anticipate Presentation to the Mayor & Commission in late 2024.

Key Project Statistics

  • Designer: TBD
  • Contractor: TBD
  • Program Manager: Jacobs Engineering
  • SPLOST Budget: $482,323
  • Grants or other funding: $400,000
  • Total Cost: TBD
  • Completion Date: TBD

Resources

Transfer Facilities Zone Map