Initial Project Statement
The initial project statement stated that Project 10 will provide for facilities to support staff functions, program and educational services, the 4-H Program, and other community events sponsored by the Athens-Clarke County Cooperative Extension Office.
Project Updates
Dedication was held September 9, 2019. The storage building, and demonstration garden are complete. Public Art is in progress and installation expected Fall 2020.
SPLOST 2011 Project Monthly Update
Key Project Statistics
- Designer: W. R. Toole Engineering, Inc.
- Program Manager: Jacobs Engineering
- Sponsor: Cooperative Extension
- Original SPLOST Budget: $2,565,000
- Amended Budget: $3,911,987
- Total Cost to Date: $3,757,133
- Completion Date: Substantially Complete October 2019
*as of 7/27/2020